|
BLACK RIVER
AND STYXX BRIDGES RE-OPENED
Minister
Robert Pickersgill on Friday, April 15, 2005, re-opened the Black
River Bridge in St. Elizabeth and the Styxx River Bridge in Westmoreland,
both of which were closed for repairs.
In
the case of the Black River Bridge, Minister Pickersgill thanked
M.P for the area, Mr. Danny Buchanan, Mayor for Black River, Mr.
Franklyn Witter, Councillor Kern Smalling and the Hendricks family
for their contribution to the rehabilitation of the bridge. (The
Hendricks family allowed access to their lands during the re-construction
of the Bridge.)
Rehabilitation
of this Bridge started in May, 2004 and included:
· The removal of corroded steel members
· Removal and replacement of troughing plates
· Sandblasting and painting of corroded tension chords, joints
and bolts
· Repairs to sidewalks and
· The re-surfacing of the bridge deck and approaches with
asphaltic concrete.
Kingston
Industrial Construction completed the works at a cost of $23.4M.
The rehabilitative activities undertaken on the Black River Truss
Bridge are part and parcel of the Ministry of Transport and Works/National
Works Agency’s Mabey & Johnson Priority Bridge programme.
Under this programme, the Ministry intends to spend just over 22.8M
pounds to complete the rehabilitation of some 40 bridges island
wide. So far 43 bridges have been identified for replacement and
two for rehabilitation. In addition, two Fords in Kingston will
be replaced with bridges; these are the Queensborough and Cassia
Park Fords. The designs for these bridges are now complete and contractors
have been invited to bid on them. Tenders were also invited for
the construction of the Hog Hole and Boswell Bridges in St. Catherine
and St. Andrew respectively.
The
Minister also used the opportunity to give an update on roadworks
taking place in the parish of St. Elizabeth. He announced that over
$67.4M has been spent to rehabilitate the Luana to Sandy Ground
main road and an additional $5.6M is being spent to clean drains
and bush over 154km of roadways in areas such as Black River, Pedro
Cross, Williamsfield, Mountainside, Tombstone, Balaclava, Newton
and Brae’s River. In total the Ministry/NWA is spending approximately
$75.1M to maintain and build roads in the parish.
And
over in Westmoreland, the Styxx Bridge work on which was started
in January, 2003 was also opened. The construction on it is part
of Phase 1 of the twenty-five million Canadian dollars (Ca$25M)
R.A Murray programme.
Construction
here was done in two phases:
PHASE
1
Tank-Weld Construction Company carried out the Bridge work component,
which included:
· Site Clearance
· Piling works
· Construction of re-inforced concrete abutments, slab deck
and
· Bridge Protection works
This
phase was completed in August 2004.
PHASE
2
In Phase 2, D.R Foote Construction Company undertook works, which
included:
· Construction of the approaches to the bridge
· Removal of existing road surface
· Preparation of formation
· Construction of Base and Surfacing using asphaltic concrete
and also
· The installation of guardrails and road markings.
These
latter were completed in March.
Minister
Pickersgill also highlighted the fact that re-habilitation work
on approximately 50km of main roads in Westmoreland valued at just
over $307M was done. These works include the Torrington to Galloway,
Truro Gate to Locust Tree, Woodstock to Newmarket to Darliston and
Albert Town to Ulster Spring main roads. The NWA has also started
repairs on five breakaways located in Lambs River, Seaford Town
and Belmont; these will cost approximately $17M.
Turning
to problems with the Kings Valley and Barham Bridges, Minister Pickersgill
noted that designs for the two structures were completed in January
and in April, contractors were invited to bid on the packages under
our Mabey and Johnson Priority Bridge programme. Tenders are expected
to be returned on May 11, 2005 after which a contract for construction
will be awarded.
|