|
MINISTER
PICKERSGILL SIGNS THREE PAJ CONTRACTS
Three contracts
pertaining to civil works at the Port Authority of Jamaica (PAJ)
were signed by Minister Robert Pickersgill on Thursday, February
12, 2004 at the Jamaica Pegasus Hotel.
The contracts
which were which were endorsed by the Government Contracts Commission
are already underway at the Ken Wright Cruise Pier in Port Antonio,
Portland and the Kingston Transshipment Terminal. The contracts
are as follows:
· The
Kingston Container Terminal Fourth Phase - Reconstruction and expansion
berths; Contractor - E. Pihl & Sons Ltd.
· The construction of a Security Boundary Wall at the Old
Zinc Factory adjacent to the Terminal. Contractor - Matrix Engineering
Works Ltd.
· The Ken Wright Cruise Pier Rehabilitation Programme in
Port Antonio for which the contractor is Tankweld Construction Ltd.
The work on
the North Terminal is particularly significant in that it was the
North Terminal that was seen as the cradle of the Kingston Container
Terminal having constructed initially in the early 1970's. Until
the mid 1990's the North Terminal was the centre of all operations.
However with the development of the South Terminal beginning in
1994 with modern infrastructure, state of the art equipment and
advanced technology, the north terminal lost its prominence and
was confined mainly to feeder traffic operations.
The scope of
this contract includes:
·
NORTH TERMINAL - demolition and re-construction of North
Terminal Berths numbers 10, 11 and 11a involving:
- demolition
of 447 metres of existing berth and construction of 502 metres
of new berths
- construction
of 5.2 hectares of container storage yard
- putting
in place the support underground services - water supply to berth
side and hydrants - surface water drainage - electrical cables
and ducts
- The contract
also calls for 630 metres of pavement to be constructed
- installation
of a high mast for the container yard extension
· construction
of a 3-storey berth side building for marine operations
In relation
to the South Terminal the contract provides for:
- The construction
of 91 metres of berth extension, plus 75 metres of return
- construction
of 7.7 hectares of additional container storage yard
- underground
services - water supply to berth side and hydrants - surface water
drainage - electrical ducts and cables
- 620 square
metres pavement construction with concrete paved block surfacing.
The cost of
the contract is US$46M.
The implementation
of the contract has been scheduled for 21 months in two phases as
follows:
- Phase 1 -
fifteen months
- Phase 2
- six months.
To be completed
about July, 2006
Overall, this
contract will serve to expand capacity, enhance operational efficiency
and berthing convenience at the Terminal both of which are important
to meet the challenges of fierce competition in both the regional
and international market.
Construction
of Security Boundary Wall - Old Zinc Factory
Another contract
related to the Kingston Container Terminal is for the construction
of a boundary wall at the old Zinc Factory building which is adjacent
to the north Western boundary of the Terminal.
This property
is being refurbished and prepared to facilitate relocation of a
company currently located in the Kingston Free Zone. The Fourth
Phase expansion of the Terminal involves encroachment on a on a
portion of the Kingston Free Zone property on the east, adjacent
to the North Terminal. Under this contract, a security boundary
wall of 264 metres and 3.15 metres high will be constructed. The
wall is to be fortified with installation atop galvanized razor
wires supported by steel fabricated gates. The contract is in the
amount of J$13,993,748.00 and is scheduled to be completed in seventeen
weeks.
Rehabilitation
of Ken Wright Cruise Ship Pier, Port Antonio
For the Ken
Wright Cruise Pier, the contract sum will be J$6, 315,660.00 and
will be focused on the pier involving the replacement of twelve
H-Piles which support the East Dolphin pier.
Since the transfer
of total cruise shipping operations to the Port Authority, initiatives
have been underway to expand and upgrade all cruise shipping facilities.
Dredging programmes designed to enhance the depth and width of sea-lanes
have been undertaken at the ports of Montego Bay and Port Antonio
to accommodate the new generation of large ships. Since the current
cruise ship season, several ship calls have been made to Port Antonio.
Under the Ministry's
capital programmes, recognition has been given to the recent trend
of port development, which directly links infrastructure to security.
Thus while expansion is going on diligence has been employed in
putting in place the equipment, systems and procedures required
to meet the security standards specified under the I.M.O.I.S.P.S
Codes. This is necessary for the certification of ports in order
to ensure Jamaica's continued participation in world trade as well
as for protecting the industry.
|