|
MINISTER
PICKERSGILL GIVES UPDATE ON MINISTRY PROJECTS

Minister Pickersgill addressing the Press Conference, partially
hidden is State Minister, Dr. Fenton Ferguson.
Minister
Robert Pickersgill gave a comprehensive update on projects falling
under the purview of the Ministry of Transport and Works at a Press
Conference held at the Jamaica Pegasus Hotel on Wednesday, February
1.
Also
present at the Press Conference were Chairmen and Heads of Agencies
who along with Ministers Pickersgill and Ferguson fielded questions
from the Press.
Among
the matters dealt with were those relating to the Road Maintenance
Fund, Highway 2000, the Northern Coastal Hihgway Improvement Project
(NCHIP), National Road Services Improvement Project (NRSIP), the
Jamaica Bridge Development Project, seaports, airports, the Half
Way Tree Transportation Centre, the Transport Authority, the Road
Safety Unit, the JUTC, Montego Bay Metro, AEROTEL, the Toll Authority,
the Port Security Corps and the Maritime Authority of Jamaica.
With
respect to the Road Maintenance Fund, it (the Fund) was very busy
doing repair work subsequent to the various hurricanes and flooding.
On its behalf, the NWA engaged in road repairs resulting in road
clean-up and restoration in a relatively short time. 34 contract
packages for maintenance work were approved at a cost of $117.3M
Projects completed under the Fund, included the Dunrobin Avenue/Constant
Spring Road junction ($24M), the Constant Spring/Shortwood Road
junction improvement($8M), the Barbican Road/Russell Heights Road
junction Phase 1($8M) and the East Kings House Road Bridge expansion
Phase 1($6M).
Highway
2000
Works on the Portmore Causeway are on schedule and a small section
between the Hunts Bay Bridge and the Fort Augusta Interchange has
been opened to traffic since December 2005. The Hunts Bay Bridge
should be completed by the end of February 2006 and the rest of
the works by the end of June 2006. After the commissioning of the
tolling equipment, it is expected that the road will be opened to
tolled vehicular traffic on or before the end of July 2006.
It is expected that Phase 1b which is between Sandy Bay and Williamsfield
, will not start until late 2007. This, because there is a need
for the Developer to monitor the flow of traffic on Phase 1A and
to realise revenues from that section which will be utilised in
the financing of Phase 1B. NROCC is currently investigating the
possibility of constructing the Spanish Town to Ocho Rios leg of
Highway 2000 before the Sandy Bay to Williamsfield construction.
SEGMENT
2 - NCHIP
This Project is approximately 70% complete and a budget of $907M
is required to complete this Segment and a further J$1.5B for the
dualisation of the Highway between Sangster Airport Roundabout and
Barrett Hall. The completion of this Segment is critical as it will
support the construction of some 11,000 rooms through developments
sucg as Ibero Star, Harmony Cove and Palmyra Resorts.
SEGMENT
3 – NCHIP
Ground was recently broken for the construction of this Phase of
the project. It is funded through grant assistance from the European
Union. The civil works contract was awarded to E. Pihl and Sons
A.S in the amount of J$689,862,360. The civil works contract will
be 100% funded by the EU.
NATIONAL
ROAD SERVICES IMPROVEMENT PROJECT (NRSIP)
This programme which is being implemented over three years with
assistance from the IDB, gives emphasis to the routine maintenance
of roadways to prevent further deterioration. This will strengthen
the NWA’s capacity to implement and manage in the short term
a nationwide maintenance programme and in the medium term, major
construction and rehabilitation activities. Construction works with
the project is expected to be financed jointly by the IDB and funding
from the Road Maintenance Fund. US$6M is needed to support the award
of three year maintenance contracts in the pilot parishes of Westmoreland,
Manchester, St. Catherine, St. Thomas and Portland.
PORT
AUTHORITY OF JAMAICA (PAJ)
In 2005, the Port of Kingston attained the 56th ranking among the
World’s Top 100 container ports and retained its position
as the leading transshipmnent port in the Latin American and Caribbean
region.
Phase 4 (KCT4) of the expansion programme of the port was completed
on time and within budget raising capacity of the port to 1.5 million
TEU’s. Between January and November 2005, 1.394 million TEU’s
were handled by the port compared to 1.109 million TEU’s during
the same period in 2004, a 25.71% increase.
Kingston
Container Terminal Expansion Phase 5
The project objective here is to increase the Terminal’s capacity
from 1.5million TEU’s to 3.2 million TEU’s by 2009.
This is to be achieved by the construction of 482 metres of berth
and the construction of 65 hectares of container yard to include
underground ducts and high mast lights.
AIRPORTS
AUTHORITY OF JAMAICA (AAJ)
Sangster Airport
Phase 1B of the capital development programme was completed at the
end of 2005 at a cost of US48.5 million. A new eleven-gate airside
concourse is now in place (with the capacity to accommodate six
wide-body aircraft) complete with gate lounges, passenger loading
bridges and thirteen new retail and food outlets. The ICAO standard
for the separation of arriving and departing passengers has been
thus addressed. Phase 2 of the programme is underway and is ahead
of the mandatory 2008 commencement date. The work is scheduled to
be completed in mid-2008 at approximately US$65.0M.
Norman
Manley Airport
Major construction works for the expansion of the airport are projected
to commence in 2006, following the completion of the preparatory/interim
works which commenced in early 2005. Phase 1a of development will
result in the construction of a new three-level departure concourse
of approximately 10,000 sq metres which will be integrated with
the existing Ticketing Concourse. The new and re-developed ticketing
area will accommodate 54 check-in desks, and to support the airlines
and build efficiencies the Common Use Terminal System (CUTS) will
be introduced. The Ticketing area will also have the capacity to
accommodate well-wishers within the terminal. A significantly improved
area will also be available for passport control and for security
check. On the 3rd floor of the Concourse, a new Departure Lounge
with retail offerings and facilities to comfortably accommodate
passengers will be erected; this development will also result in
passenger loading bridges being installed.
TRANSPORT
AUTHORITY
During the period April 2005 to November 2005, a total of 25,982
licences were issued, broken down as follows:
(a) Route Taxi 10,008
(b) Rural Stage 415
© Hackney Cge 791
(d) Contract Cge. 1,844
(e) Public Carrier 3,255
(f) Private Carrier 9,669
A
total of 12,670 prosecutions were carried out resulting in a total
of $18,964,629 being paid into the Consolidated Fund. The operational
arm was strengthened with the re-establishment of joint operations
with the Island Special Constabulary Force. Sixty police officers
have been assigned to the Authority.
MOBAY
METRO
For the period April 2005 to January 2006, Montego Bay continues
to operate on three routes and in September 2005, a second dedicated
route to Ruseas High School was added as requested by the school.
The company now operates on three municipal routes and three dedicated
school routes, these being: Greenwood to City Centre; Sandy Bay
to City Centre and Cambridge to City Centre. The dedicated school
routes are Merlene Ottey High School; Knockalva High School and
Ruseas High School.
JAMAICA
URBAN TRANSIT COMPANY (JUTC)
Revenue for April, 2005-December 2005 amounted to $1,915.28B, an
increase of 16.32% over the corresponding period in 2004. Ridership
for April-December, 2005 amounted to 56.34 million , a decrease
of 2.09% vs. the corresponding period in 2004.
A campaign was initiated to increase the use of Smart Cards. This
resulted in a doublig of users to 7% and Point of Sale locations
moving from 18 to 47. including 19 schools.
Nine
timetables were published and erected in the eastern region. This
is a part of the commitment given to improve customer service. A
revenue protection programme introduced to reduce the number of
free riders on the buses has proven quite effective. The JUTC intends
to continue working closely with the National Works Agency and install
a number of cameras at key points in the Corporate Area to monitor
operations and improve safety, efficiency and regulation of the
KMTR. The company also plans to install cameras on buses in the
coming year also as part of its safety and risk management programme.
TOLL
AUTHORITY
During the year, the Authority commissioned a review of the signs
of the highway; this was conducted by NWA on the Authority’s
behalf. Instructions for amendments and adjustments of some signs
were subsequently submitted to the Trans Jamaica Highway as the
body responsible for corrections.
The
Authority recently retained the NWA to conduct an audit of roads.
In this Audit, the Agency will provide:
• Review of design hydraulics and actual operations
• Review of Quality Assurance
• Review of traffic queues, signage
• Desktop review of all built drawings
• Field/Site visits
• Advise on the acceptability of the designs and all works
constructed in relation to accepted international highway construction,
design, drainage and bridge designs.
The
Authority processed 36 calls since the beginning of the financial
year, a 55% reduction in complaints when compared with to the previous
year’s figure of 80.
|