Project-At-A-Glance |
| Project Name |
Northern Coastal Highway Improvement Project – Segment 2 |
| Start Date |
January, 2003 |
| Completion Date |
December, 2006 |
| Cost |
US$146M |
| Contractor |
Jose Cartellone Civiles |
| Funding |
IDB and GOJ |
| Project Objective |
To foster long term economic diversification and growth in the tourism sector by improving road conditions. |
|
|
| Scope of Works |
- Construction of the Martha Brae River Bridge, the River Bueno Bridge; the Pear Tree River Bridge; Wakefield Interchange.
- Re-construction and re-alignment of 4 Bypasses to the towns of Falmouth, Duncans, Rio Bueno and Coopers Pen
- Overlay of 11km of existing roadway
- Construction of two Underpasses to facilitate livestock movement on either side of the roadway
- Construction of two vehicular Underpasses at Silver Sands Road in Duncans and Calabar main road in Rio Bueno
- Construction of one golf cart and pedestrian Underpasses at Breezes, Runaway bay
- Provision of over five right turn lanes at major intersections and entrances to enhance safety.
- Provision of traffic lights at critical intersections to enhance safety
|
|
|
|